Milestones

AWZI Harnaschpolder kantoor

General

  • 15-01-2003 – Order to proceed
  • 04-12-2003 – Contract close
  • 31-05-2008 – Service Delivery

 

AWZI Harnaschpolder luchtfoto

Harnaschpolder

  • 01-10-2003 – Construction work commenced
  • 01-09-2006 – Starting up treatment
  • 18-12-2006 – Availability of Capacity Intermediate
  • 31-05-2008 – Availability of Capacity 100%
  • 30-06-2008 – Completion Certificate
AWZI Houtrust luchtfoto

Houtrust

  • 08-01-2007 – Start of Phase 1 upgrade works
  • 03-10-2007 – Availability of 50% Capacity
  • 04-10-2007 – Start of Phase 2 upgrade works
  • 31-05-2008 – Availability of Capacity 100%
  • 31-12-2009 – Completion Certificate
Houtrust biologische tanks, veraf

Transport System

  • 01-06-2006 – Influent transport system available
  • 01-06-2006 – Effluent transport system available
Houtrust leidingwerk detail

Financial

  • 05-12-2003 – Financial close
  • 30-01-2009 – Repayment of Junior Funds Bridge
  • 15-06-2009 – First Repayment date of Senior Debt
  • 21-11-2011 – EIB Guarantee Release
  • 15-06-2016 – Restructuring of the finance